As COVID-19 continues to result in government shutdown orders, labor shortages, and increased lead times to acquire materials, project owners, contractors, and subcontractors may begin to make claims of “force majeure,” or may otherwise suspend or even terminate work. Often these notifications or ...
MoreThe subcontractor did everything right: it did the work, but did not get paid, and thereafter properly perfected a lien. Now, the subcontractor has an opportunity to settle with the general contractor or even its subsequent bankruptcy trustee. The subcontractor needs to proceed with caution to avoid losing its ...
MoreRecent Posts
- The Importance of Change Orders on Construction Claims
- Owners’ Rights Pursuing Claims Directly Against Subcontractors/Vendors
- The Initial Decision Maker: Coordinating the Owner-Architect and Owner-Contractor Agreements
- Understanding the Texas Prompt Payment Act
- What do you mean I don’t own the plan?
- Key Considerations to Perfect Performance Bond Claims in Texas
- The Owner’s Dos and Don’ts When a General Contractor Files for Chapter 11 Bankruptcy
- The Sweeping Application of the Texas Construction Anti-Indemnity Act
- New Texas Legislation that Restricts Owner-Directed Change Order Rights Takes Effect September 1, 2023
- Strict Deadlines Apply to Motions to Vacate Arbitration Awards Under the Federal and Texas Arbitration Acts
TopicsSelect Category
ArchivesSelect Month
- October 2024
- August 2024
- July 2024
- March 2024
- February 2024
- November 2023
- September 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- October 2022
- September 2022
- June 2022
- May 2022
- April 2022
- March 2022
- November 2021
- August 2021
- July 2021
- June 2021
- May 2021
- March 2021
- February 2021
- January 2021
- August 2020
- June 2020
- May 2020
- March 2020
- January 2020
- December 2019
- October 2019
- May 2019
- April 2019
- March 2019
- February 2019
- January 2019
- November 2018
- September 2018
- August 2018
- June 2018
- May 2018