As COVID-19 continues to result in government shutdown orders, labor shortages, and increased lead times to acquire materials, project owners, contractors, and subcontractors may begin to make claims of “force majeure,” or may otherwise suspend or even terminate work. Often these notifications or ...
MoreUnlike with private commercial projects, liens cannot be filed against public projects in Texas. This means that unpaid subcontractors and suppliers do not have the same protections on public projects as those on private projects. On a private project, a subcontractor or supplier would ordinarily file a lien ...
MoreTexas law has certain peculiarities which must be followed when a project is located in Texas. To avoid surprises and unanticipated liability on construction projects, the parties should modify contracts consistent with Texas law—or at least be aware of the limitations that are in place due to certain Texas ...
MoreWhat should a Subcontractor do when a General Contractor presents, to the Subcontractor, the 401A-2017 Standard Form of Agreement Between Contractor and Subcontractor (“A401”)? While some provisions in the A401 are favorable to the Subcontractor, others are not. This multi-part series explores some of the ...
MoreCommercial construction contracts between owners and contractors, such as the form AIA Document A201 contract, often include various express warranties whereby the contractor warrants its work on the project to the owner. Among those express warranties are the more common warranties that: (i) the materials and ...
MoreAs described by my colleague Sean McChristian in Part 1 of this two-part blog series, planning for hurricane season in Texas is a critical part of mitigating risk in the construction industry. In addition to reviewing force majeure provisions, owners and contractors need to have an understanding of the ...
MoreThe Gulf Coast hurricane season runs from June 1st to November 30th each year. Because this is a known risk, many businesses prepare emergency response plans to mitigate risks to persons and property, but many of those same businesses are not prepared to mitigate economic risks arising from ongoing construction ...
MoreSubcontracts between a general contractor and subcontractor often contain a flow-down provision stating that the terms and conditions in the owner/contractor agreement (the “Prime Contract”) are also binding on the subcontractor—making the subcontractor obligated to provisions in the Prime ...
MoreRecent Posts
- The Importance of Change Orders on Construction Claims
- Owners’ Rights Pursuing Claims Directly Against Subcontractors/Vendors
- The Initial Decision Maker: Coordinating the Owner-Architect and Owner-Contractor Agreements
- Understanding the Texas Prompt Payment Act
- What do you mean I don’t own the plan?
- Key Considerations to Perfect Performance Bond Claims in Texas
- The Owner’s Dos and Don’ts When a General Contractor Files for Chapter 11 Bankruptcy
- The Sweeping Application of the Texas Construction Anti-Indemnity Act
- New Texas Legislation that Restricts Owner-Directed Change Order Rights Takes Effect September 1, 2023
- Strict Deadlines Apply to Motions to Vacate Arbitration Awards Under the Federal and Texas Arbitration Acts
TopicsSelect Category
ArchivesSelect Month
- October 2024
- August 2024
- July 2024
- March 2024
- February 2024
- November 2023
- September 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- October 2022
- September 2022
- June 2022
- May 2022
- April 2022
- March 2022
- November 2021
- August 2021
- July 2021
- June 2021
- May 2021
- March 2021
- February 2021
- January 2021
- August 2020
- June 2020
- May 2020
- March 2020
- January 2020
- December 2019
- October 2019
- May 2019
- April 2019
- March 2019
- February 2019
- January 2019
- November 2018
- September 2018
- August 2018
- June 2018
- May 2018