With material cost volatility in the current market, the topic of price escalation clauses is more prevalent. Some material costs are up and other costs are now down. Traditional lump sum contract structures do not take into account price escalation or de-escalation; whereas cost plus structures entirely and naturally account for such changes. Owners of construction projects tend to prefer lump sum projects due to certainty in budgeting and other reasons.
A potential mechanism to account for volatility is to include a price escalation clause. This blog post provides the basics of such a clause and asks questions to consider when drafting.
What is a price escalation clause?
- A clause utilized to account for price fluctuation in construction costs for specifically identified materials particularly susceptible to fluctuation (i.e. steel, lumber)
What are the benefits of a price escalation clause for an owner?
- The risk of overpricing materials is reduced
- Such a clause may allow a project to move forward in an uncertain market and may even expand the number of bidders
What are the drawbacks of a price escalation clause for an owner?
- The risk of a price increase is shifted to owner
What are the benefits of a price escalation clause for a contractor?
- The contractor is protected if market conditions worsen
What are the drawbacks of a price escalation clause for a contractor?
- Price escalation clauses may take away upside from the contractor for taking on greater risk
- Additionally, more cost information must be disclosed by the contractor
What are some of the best practices for drafting a price escalation clause?
- Identify the materials to which the clause applies
- Define the baseline cost upon which the contract pricing is based
- Define the price increase/decrease that triggers the clause – material prices must increase/decrease by a certain amount or a percentage over the base amount before the clause is triggered
- Consider whether the clause will be cost-based or index-based
- The clause should include a written notice requirement tied to when the counterparty becomes aware of the material price increase or decrease
If you need help in drafting a price escalation clause, hire an attorney. These clauses are complicated and require both parties to consider multiple legal and commercial terms.
- Partner
Amy Wolfshohl is certified by the Texas Board of Legal Specialization in Construction Law and has been recognized by Chambers USA, The Legal 500, The Best Lawyers in America, and Super Lawyers for Construction Law. Chambers sources ...
Recent Posts
- Choice of Law and Federal Preemption: Why Texas Law May Not Govern Your Texas Project Despite the Home Rule Statute
- The Importance of Change Orders on Construction Claims
- Owners’ Rights Pursuing Claims Directly Against Subcontractors/Vendors
- The Initial Decision Maker: Coordinating the Owner-Architect and Owner-Contractor Agreements
- Understanding the Texas Prompt Payment Act
- What do you mean I don’t own the plan?
- Key Considerations to Perfect Performance Bond Claims in Texas
- The Owner’s Dos and Don’ts When a General Contractor Files for Chapter 11 Bankruptcy
- The Sweeping Application of the Texas Construction Anti-Indemnity Act
- New Texas Legislation that Restricts Owner-Directed Change Order Rights Takes Effect September 1, 2023
TopicsSelect Category
ArchivesSelect Month
- December 2024
- October 2024
- August 2024
- July 2024
- March 2024
- February 2024
- November 2023
- September 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- October 2022
- September 2022
- June 2022
- May 2022
- April 2022
- March 2022
- November 2021
- August 2021
- July 2021
- June 2021
- May 2021
- March 2021
- February 2021
- January 2021
- August 2020
- June 2020
- May 2020
- March 2020
- January 2020
- December 2019
- October 2019
- May 2019
- April 2019
- March 2019
- February 2019
- January 2019
- November 2018
- September 2018
- August 2018
- June 2018
- May 2018