On February 17, 2022, the Court of Appeals in El Paso, Texas reversed a summary judgment in favor of a mineral lien subcontractor claimant because, at the time the lien was filed, nothing further was owed under the prime agreement (Pearl Res. Operating Co. LLC v. Transcon Capital, LLC, No. 08-19-00288-CV, 2022 WL 484546, at *1 (Tex. App.—El Paso Feb. 17, 2022, no pet. h.)).
Background
The contract at issue obligated Pearl Operating, as owner, to make an initial upfront payment to PDS Drilling LLC (PDS), the drilling contractor, of 30 percent of that total amount after PDS positioned a rig at the well site ready to spud. Thereafter, Pearl Operating was required to pay PDS the remaining 70 percent within five business days after PDS had delivered a successful well and had invoiced Pearl Operating for its services. The contract expressly stated that PDS needed to satisfy both conditions before Pearl Operating would have to pay the remaining amounts due.
While undertaking the work, the well suffered a wild well incident. The lien claimant was engaged by PDS to provide emergency services to contain the water flow at the well site. Thereafter, PDS abandoned the work. Before PDS’s abandonment, the lien subcontractor claimant sent two invoices to PDS requesting payment. After PDS failed to pay, the lien claimant attempted to perfect a mineral lien.
The lien claimant argued for a mineral lien because Pearl Operating had not paid all amounts owed under the prime agreement. Pearl Operating argued there was no lien because PDS was not entitled to further payment under the prime agreement. The appellate court sided with Pearl Operating because “a mineral lien under Chapter 56 is dependent upon the state of the account between the owner and its contractor, and not upon the condition of the account between the contractor and subcontractor, when the owner receives notice of the claim.” Id. at *5. Here, because the owner had already paid its contractor all that is owed under the contract when the lien claimant served notice of its claim, the subcontractor was not entitled to the lien.
Lessons Learned
For owners, paying final amounts due to contractors on mineral lien projects does not carry the same risk as projects subject to mechanic’s liens. Specifically, if no subcontractors have served notices when the final amount is paid, the owner is not subject to subcontractor lien liability. On the other hand, mineral lien claimants should not wait for extended periods to claim mineral liens because there may be no lien right despite having met the lengthy deadlines available under Chapter 56.
- Partner
Amy Wolfshohl is certified by the Texas Board of Legal Specialization in Construction Law and has been recognized by Chambers USA, The Legal 500, The Best Lawyers in America, and Super Lawyers for Construction Law. Chambers sources ...
Recent Posts
- The Importance of Change Orders on Construction Claims
- Owners’ Rights Pursuing Claims Directly Against Subcontractors/Vendors
- The Initial Decision Maker: Coordinating the Owner-Architect and Owner-Contractor Agreements
- Understanding the Texas Prompt Payment Act
- What do you mean I don’t own the plan?
- Key Considerations to Perfect Performance Bond Claims in Texas
- The Owner’s Dos and Don’ts When a General Contractor Files for Chapter 11 Bankruptcy
- The Sweeping Application of the Texas Construction Anti-Indemnity Act
- New Texas Legislation that Restricts Owner-Directed Change Order Rights Takes Effect September 1, 2023
- Strict Deadlines Apply to Motions to Vacate Arbitration Awards Under the Federal and Texas Arbitration Acts
TopicsSelect Category
ArchivesSelect Month
- October 2024
- August 2024
- July 2024
- March 2024
- February 2024
- November 2023
- September 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- October 2022
- September 2022
- June 2022
- May 2022
- April 2022
- March 2022
- November 2021
- August 2021
- July 2021
- June 2021
- May 2021
- March 2021
- February 2021
- January 2021
- August 2020
- June 2020
- May 2020
- March 2020
- January 2020
- December 2019
- October 2019
- May 2019
- April 2019
- March 2019
- February 2019
- January 2019
- November 2018
- September 2018
- August 2018
- June 2018
- May 2018